Indirect Costs - Indirect Vs Direct Costs

Indirect Vs Direct Costs

Most cost estimates are broken down into direct costs and indirect costs.

Direct costs are directly attributable to the cost object. In construction, the costs of materials, labor, equipment, etc, and all directly involved efforts or expenses for the cost object are direct costs. In manufacturing or other non-construction industries the portion of operating costs that is directly assignable to a specific product or process is a direct cost. Direct costs are those for activities or services that benefit specific projects, for example salaries for project staff and materials required for a particular project. Because these activities are easily traced to projects, their costs are usually charged to projects on an item-by-item basis.

Indirect costs are not directly attributable to a cost object. Indirect costs are typically allocated to a cost object on some basis. In construction, all costs which are required for completion of the installation, but are not directly attributable to the cost object are indirect, such as overhead. In manufacturing, costs not directly assignable to the end product or process are indirect. These may be costs for management, insurance, taxes, or maintenance, for example. Indirect costs are those for activities or services that benefit more than one project. Their precise benefits to a specific project are often difficult or impossible to trace. For example, it may be difficult to determine precisely how the activities of the director of an organization benefit a specific project. Indirect costs do not vary substantially within certain production volumes or other indicators of activity, and so they may sometimes be considered to be fixed costs.

It is possible to justify the handling of almost any kind of cost as either direct or indirect. Labor costs, for example, can be indirect, as in the case of maintenance personnel and executive officers; or they can be direct, as in the case of project staff members. Similarly, materials such as miscellaneous supplies purchased in bulk—pencils, pens, paper—are typically handled as indirect costs, while materials required for specific projects are charged as direct costs.

Read more about this topic:  Indirect Costs

Famous quotes containing the words indirect, direct and/or costs:

    Imagination is always the fabric of social life and the dynamic of history. The influence of real needs and compulsions, of real interests and materials, is indirect because the crowd is never conscious of it.
    Simone Weil (1909–1943)

    Forty years after a battle it is easy for a noncombatant to reason about how it ought to have been fought. It is another thing personally and under fire to have to direct the fighting while involved in the obscuring smoke of it.
    Herman Melville (1819–1891)

    To exercise power costs effort and demands courage. That is why so many fail to assert rights to which they are perfectly entitled—because a right is a kind of power but they are too lazy or too cowardly to exercise it. The virtues which cloak these faults are called patience and forbearance.
    Friedrich Nietzsche (1844–1900)