Portlands Energy Centre - Power Purchase Agreement, Timing and Capital Costs

Power Purchase Agreement, Timing and Capital Costs

On September 18, 2006, TransCanada issued a press release announcing that Portlands Energy Centre L.P. had signed a 20-year Accelerated Clean Energy Supply (ACES) contract with the Ontario Power Authority for the power output of the PEC.

The plant started delivering 340 MW of power to the City of Toronto in June 2008 in single-cycle operation and was fully operational with an output of 550 MW by the second-quarter 2009. Total capital costs are expected to reach $730MM.

Read more about this topic:  Portlands Energy Centre

Famous quotes containing the words power, purchase, timing, capital and/or costs:

    It is probable that the principal credit of miracles, visions, enchantments, and such extraordinary occurrences comes from the power of imagination, acting principally upon the minds of the common people, which are softer.
    Michel de Montaigne (1533–1592)

    Riches are valuable at all times, and to all men; because they always purchase pleasures, such as men are accustomed to, and desire: Nor can any thing restrain or regulate the love of money, but a sense of honour and virtue; which, if it be not nearly equal at all times, will naturally abound most in ages of knowledge and refinement.
    David Hume (1711–1776)

    A great man always considers the timing before he acts.
    Chinese proverb.

    It is a capital mistake to theorize before one has data.
    Sir Arthur Conan Doyle (1859–1930)

    It is commonly said by farmers, that a good pear or apple costs no more time or pains to rear, than a poor one; so I would have no work of art, no speech, or action, or thought, or friend, but the best.
    Ralph Waldo Emerson (1803–1882)