Critical Chain Project Management - Details

Details

With traditional project management methods, 30% of the lost time and resources are typically consumed by wasteful techniques such as bad multi-tasking, student syndrome, In-box delays, and lack of prioritization.

In project management, the critical chain is the sequence of both precedence- and resource-dependent terminal elements that prevents a project from being completed in a shorter time, given finite resources. If resources are always available in unlimited quantities, then a project's critical chain is identical to its critical path.

Critical chain is used as an alternative to critical path analysis. The main features that distinguish the critical chain from the critical path are:

  1. The use of (often implicit) resource dependencies. Implicit means that they are not included in the project network but have to be identified by looking at the resource requirements.
  2. Lack of search for an optimum solution. This means that a "good enough" solution is enough because:
    1. As far as is known, there is no analytical method of finding an absolute optimum (i.e. having the overall shortest critical chain).
    2. The inherent uncertainty in estimates is much greater than the difference between the optimum and near-optimum ("good enough" solutions).
  3. The identification and insertion of buffers:
    • project buffer
    • feeding buffers
    • resource buffers. (Most of the time it is observed that companies are reluctant to give more resources)
  4. Monitoring project progress and health by monitoring the consumption rate of the buffers rather than individual task performance to schedule.

CCPM planning aggregates the large amounts of safety time added to tasks within a project into the buffers in order to protect due-date performance, and to avoid wasting this safety time through bad multitasking, student syndrome, Parkinson's Law and poorly synchronized integration.

Critical chain project management uses buffer management instead of earned value management to assess the performance of a project. Some project managers feel that the earned value management technique is misleading, because it does not distinguish progress on the project constraint (i.e. on the critical chain) from progress on non-constraints (i.e. on other paths). Event chain methodology can be used to determine a size of project, feeding, and resource buffers.

Read more about this topic:  Critical Chain Project Management

Famous quotes containing the word details:

    There was a time when the average reader read a novel simply for the moral he could get out of it, and however naïve that may have been, it was a good deal less naïve than some of the limited objectives he has now. Today novels are considered to be entirely concerned with the social or economic or psychological forces that they will by necessity exhibit, or with those details of daily life that are for the good novelist only means to some deeper end.
    Flannery O’Connor (1925–1964)

    Working women today are trying to achieve in the work world what men have achieved all along—but men have always had the help of a woman at home who took care of all the other details of living! Today the working woman is also that woman at home, and without support services in the workplace and a respect for the work women do within and outside the home, the attempt to do both is taking its toll—on women, on men, and on our children.
    Jeanne Elium (20th century)

    Different persons growing up in the same language are like different bushes trimmed and trained to take the shape of identical elephants. The anatomical details of twigs and branches will fulfill the elephantine form differently from bush to bush, but the overall outward results are alike.
    Willard Van Orman Quine (b. 1908)