As of November 2008, crews had completed concrete work two months ahead of schedule, wrapping up the concrete portion of construction with a roof deck pour for the Twins administration building, according to the Minnesota Ballpark Authority. In March 2009 Tekna Kleen (commercial cleaning company), started doing the finishing cleaning touches to Target Field. In late August, 2009, the playing field was installed.