Columbia River Crossing - Proposal

Proposal

A draft environmental impact statement (EIS) was published in May 2008, with a final EIS published in the Federal Register on September 23, 2011. While first said to begin in 2010, the CRC team later said construction would not begin until late 2014. The EIS was produced at a cost of $105 million, over five times the original estimate, and was delivered 18 months behind schedule. The ongoing project planning costs $1 million per month. Planners say the construction phase would last five to seven years. Official cost estimates for a phased build-out were $2.8 billion, down from earlier estimates of $3.5 billion. The CRC finance plan called for tolling to pay for up to $1.3 billion of the cost.