William R. Bennett Bridge - Construction Schedule

Construction Schedule

  • April 2005: Arthon Construction Ltd. begins bridge end preloads from rock on Westside Road
  • May 2005: Arthon completes east side preload
  • June 2005: SNC-Lavalin Inc. is chosen to design, build, finance and operate the new bridge
  • July 2005: Construction begins on a dry dock near Bear Creek Provincial Park, where the bridge pontoons will be built
  • Q3 2005: Arthon completes preloads on west side of Lake Okanagan
  • Q3 2005: Graving dock ready
  • Q3 2006: Roadwork on both approaches begins
  • Q4 2006: First four pontoons in place
  • Q1 2007: Bridge deck construction begins
  • Q4 2007: All pontoons in place
  • Q4 2007: Roadwork on both approaches is completed
  • Q1 2008: Bridge deck construction is completed
  • Q2 2008: Test and commission
  • Q2 2008: Bridge officially opens
    • Official opening scheduled for May 25, 2008
  • Q2 2009: Decommission of the old bridge
  • Q2 2009: Shoreline restoration

Read more about this topic:  William R. Bennett Bridge

Famous quotes containing the word construction:

    There’s no art
    To find the mind’s construction in the face:
    He was a gentleman on whom I built
    An absolute trust.
    William Shakespeare (1564–1616)