Construction Schedule
- April 2005: Arthon Construction Ltd. begins bridge end preloads from rock on Westside Road
- May 2005: Arthon completes east side preload
- June 2005: SNC-Lavalin Inc. is chosen to design, build, finance and operate the new bridge
- July 2005: Construction begins on a dry dock near Bear Creek Provincial Park, where the bridge pontoons will be built
- Q3 2005: Arthon completes preloads on west side of Lake Okanagan
- Q3 2005: Graving dock ready
- Q3 2006: Roadwork on both approaches begins
- Q4 2006: First four pontoons in place
- Q1 2007: Bridge deck construction begins
- Q4 2007: All pontoons in place
- Q4 2007: Roadwork on both approaches is completed
- Q1 2008: Bridge deck construction is completed
- Q2 2008: Test and commission
- Q2 2008: Bridge officially opens
- Official opening scheduled for May 25, 2008
- Q2 2009: Decommission of the old bridge
- Q2 2009: Shoreline restoration
Read more about this topic: William R. Bennett Bridge
Famous quotes containing the word construction:
“When the leaders choose to make themselves bidders at an auction of popularity, their talents, in the construction of the state, will be of no service. They will become flatterers instead of legislators; the instruments, not the guides, of the people.”
—Edmund Burke (17291797)