USS Zumwalt (DDG-1000) - History

History

See also: Zumwalt class destroyer#History

Many of the ship's features were originally developed under the DD21 program ("21st Century Destroyer"). In 2001, Congress cut the DD-21 program by half as part of the SC21 program; to save it, the acquisition program was renamed as DD(X) and heavily reworked. The initial funding allocation for DDG-1000 was included in the National Defense Authorization Act of 2007.

A contract worth $1.4bn was awarded to General Dynamics on 14 February 2008, for the construction of USS Zumwalt at Bath Iron Works in Bath, Maine.

Full rate production officially began on 11 February 2009.

As of July 2008, the construction timetable was for General Dynamics to deliver the ship in April 2013, with March 2015 as the target for Zumwalt to meet her initial operating capability. However, by 2012, the planned completion and delivery of the vessel had slipped to Fiscal Year 2014.

The first section of the ship was laid down on the slipway at Bath Iron Works on 17 November 2011. By this point, fabrication of the ship was over 60% complete.

Read more about this topic:  USS Zumwalt (DDG-1000)

Famous quotes containing the word history:

    The history of all countries shows that the working class exclusively by its own effort is able to develop only trade-union consciousness.
    Vladimir Ilyich Lenin (1870–1924)

    Perhaps universal history is the history of the diverse intonation of some metaphors.
    Jorge Luis Borges (1899–1986)

    Racism is an ism to which everyone in the world today is exposed; for or against, we must take sides. And the history of the future will differ according to the decision which we make.
    Ruth Benedict (1887–1948)