Southern California Edison - Renewable Energy

Renewable Energy

In 2009 Southern California Edison entered into a contract with Solar Millennium to purchase solar thermal power up to 726 MW.

Southern California Edison also entered into a contract with Stirling Energy Systems to buy electricity from a 500 megawatt, 4,600 acre (19 kmĀ²), solar power plant which was due to open in 2009. The purchase was canceled in late 2010, as changes in technology reduced the cost of photovoltaic-based solar power to below that of solar Stirling generated power. This would have been the first commercial application of the dish stirling system. A different technology from the more familiar solar panel, the dish concentrates solar energy by the use of reflective surfaces and by the use of the Stirling heat engine to convert the heat into electricity.

In 2006, Southern California Edison planned to secure 1,500 megawatts or more of power generated from new projects to be built in the Tehachapi Pass Wind Farm area. The contract, which more than doubles SCE's wind energy portfolio, envisions more than 50 square miles (130 km2) of wind parks in the Tehachapi region, which is triple the size of any existing U.S. wind farm.

In March 2008, Southern California Edison announced a $875 million project to build a network of 250 megawatts of photovoltaic solar power generation, making it the biggest solar cell project in the nation. The photovoltaic cells will cover 65,000,000 square feet (6,000,000 m2) of rooftops in southern California and will generate enough power to serve 162,000 homes.

Southern California Edison received a 100% rating on the Corporate Equality Index released by the Human Rights Campaign starting in 2004, the third year of the report.

Read more about this topic:  Southern California Edison

Famous quotes containing the word energy:

    All my energy and attention were devoted to trying to help her solve her problems. Unfortunately I didn’t have much success.
    Arthur Miller (b. 1915)