Solar Updraft Tower - Financial Feasibility

Financial Feasibility

A solar updraft power station would require a large initial capital outlay, but would have relatively low operating cost.

Capital outlays would be roughly the same as next-generation nuclear plants such as the AP-1000 at roughly $5 per Watt of capacity. As with other renewable power sources, towers have no need for fuel. Overall costs are largely determined by interest rates and years of operation, varying from 5 eurocent per kWh for 4% and 20 years to 15 eurocent per kWh for 12% and 40 years.

Estimates of total costs range from 7 (for a 200 MW plant) and 21 (for a 5 MW plant) euro cents per kWh to 25-35 cents per kWh. Levelized cost are approximately 3 Euro cents per KWh for a 100 MW wind or natural gas plant. No actual data are available for a utility scale power plant.

As with other solar technologies, some mechanism is required to mix its varying power output with other power sources. Heat can be stored in heat-absorbing material or saltwater ponds. Electricity can be cached in batteries or other technologies.

Read more about this topic:  Solar Updraft Tower

Famous quotes containing the word financial:

    Because of these convictions, I made a personal decision in the 1964 Presidential campaign to make education a fundamental issue and to put it high on the nation’s agenda. I proposed to act on my belief that regardless of a family’s financial condition, education should be available to every child in the United States—as much education as he could absorb.