The reservoir requires 88 dykes to prevent overflow outside of the reservoir. The highest of these dykes is 36 m (118 ft) and the longest at 6 km (3.7 mi). The two reservoirs require three control structures to regulate flow. The Gabbro Control Structure which regulated the Ossokmanuan reservoir, the Lobstick Control Structure that regulates the Smallwood reservoir and the Whitefish Control Structure for the forebay reservoirs. Both forebays are further regulated by spillways to prevent flooding.

The project took 9 years to complete from 1966 to 1974, with peak construction in 1970 when a total of 6,245 workers were stationed at the main camp and eleven satellite camps. The project was completed five months ahead of schedule.

Read more about this topic:  Smallwood Reservoir

Famous quotes containing the word construction:

    There is, I think, no point in the philosophy of progressive education which is sounder than its emphasis upon the importance of the participation of the learner in the formation of the purposes which direct his activities in the learning process, just as there is no defect in traditional education greater than its failure to secure the active cooperation of the pupil in construction of the purposes involved in his studying.
    John Dewey (1859–1952)

    No real “vital” character in fiction is altogether a conscious construction of the author. On the contrary, it may be a sort of parasitic growth upon the author’s personality, developing by internal necessity as much as by external addition.
    —T.S. (Thomas Stearns)

    There’s no art
    To find the mind’s construction in the face:
    He was a gentleman on whom I built
    An absolute trust.
    William Shakespeare (1564–1616)