Second Severn Crossing - Construction

Construction

The crossing was built by a business consortium under a public-private partnership. A company called Severn River Crossing plc, led by John Laing plc and GTM-Entrepose, was formed to build the new crossing. The company also took over the responsibility of managing and maintaining the old Severn Bridge crossing, as well as managing and maintaining the new crossing. The cost of constructing the new crossing was expected to be paid for by tolls collected from motorists using the two crossings. Work on the new crossing began in 1992 with completion in 1996.

Sub-assemblies for the bridge were constructed onshore and then shifted by a large tracked vehicle (similar to that used to move the Apollo and Space Shuttle at Cape Kennedy) onto a barge (the SAR3), prior to being floated out on the high tide to the appropriate site. The 37 bridge pier foundations on the approach viaducts are 107.3 yards (98.1 m) apart, and consist of open concrete caissons weighing up to 2,000 tonnes, which were founded on the rock of the estuary bed. The decking consists of 3.8 yards (3.5 m) post stressed match cast sections, weighing 200 tonnes each.

The cable stayed section of the crossing is over 984 yards (899.8 m) long, consisting of a 38 yards (35 m) wide deck made from steel plate girders with a composite reinforced concrete slab. These were prefabricated on shore and put in place using balanced cantilever methods. There are two 489 feet (149 m) high twin leg, reinforced and pre-stressed concrete pylons carrying 240 cables which support the bridge deck. Cable vibrations were experienced during construction and secondary cables were added to eliminate this. To avoid detracting from the aesthetics of the primary cables, the secondary cables are very slender and are not very noticeable.

Read more about this topic:  Second Severn Crossing

Famous quotes containing the word construction:

    No construction stiff working overtime takes more stress and straining than we did just to stay high.
    Gus Van Sant, U.S. screenwriter and director, and Dan Yost. Bob Hughes (Matt Dillon)

    There is, I think, no point in the philosophy of progressive education which is sounder than its emphasis upon the importance of the participation of the learner in the formation of the purposes which direct his activities in the learning process, just as there is no defect in traditional education greater than its failure to secure the active cooperation of the pupil in construction of the purposes involved in his studying.
    John Dewey (1859–1952)

    No real “vital” character in fiction is altogether a conscious construction of the author. On the contrary, it may be a sort of parasitic growth upon the author’s personality, developing by internal necessity as much as by external addition.
    —T.S. (Thomas Stearns)