Construction Programme
- Royal Navy
| Pennant | Name | (a) Hull builder (b) Main machinery manufacturers |
Laid down | Launched | Accepted into service | Commissioned | Estimated building cost | |
|---|---|---|---|---|---|---|---|---|
| First 10, Y-100 machinery | ||||||||
| F109 | Leander | (a) & (b) Harland & Wolff Ltd, Belfast. | 10 April 1959 | 28 June 1961 | March 1963 | 27 March 1963 | £4,630,000 | |
| F104 | Dido | (a) & (b) Yarrow & Co Ltd, Glasgow. | 2 December 1959 | 22 December 1961 | September 1963 | 18 September 1963 | £4,600,000 | |
| F127 | Penelope | (a) Vickers-Armstrongs (Shipbuilders) Ltd, Newcastle (b) Vickers-Armstrongs (Engineers) Ltd, Barrow-in-Furness |
14 March 1961 | 17 August 1962 | November 1963 | 31 October 1963 | £4,600,000 | |
| F114 | Ajax | (a) & (b) Cammell Laird & Co (Shipbuilders and Engineers) Ltd, Birkenhead. | 19 October 1959 | 16 August 1962 | December 1963 | 10 December 1963 | £4,800,000 | |
| F10 | Aurora | (a) & (b) John Brown & Co Ltd, Clydebank | 1 June 1961 | 28 November 1962 | April 1964 | 9 April 1964 | £4,650,000 | |
| F18 | Galatea | (a) Swan, Hunter & Wigham Richardson Ltd, Wallsend-on-Tyne (b) The Wallsend Slipway & Engineering Co Ltd, Wallsend-on-Tyne (steam turbines) (b) Parsons Marine Turbines Co Ltd, Wallsend-on-Tyne (gearing). |
29 December 1961 | 23 May 1963 | April 1964 | 25 April 1964 | £4,500,000 | |
| F15 | Euryalus | (a) Scotts Shipbuilding & Engineering Co Ltd, Greenock (b) Scotts Shipbuilding & Engineering Co Ltd (steam turbines) (b) Fairfield Shipbuilding & Engineering Co Ltd, Glasgow (gearing). |
2 November 1961 | 6 June 1963 | September 1964 | 16 September 1964 | £4,350,000 | |
| F39 | Naiad | (a) Yarrow & Co Ltd, Glasgow (b) Yarrow & Co Ltd, Glasgow (steam turbines) (b) Parsons Marine Turbines Co Ltd, Wallsend-on-Tyne (gearing). |
30 October 1962 | 4 November 1963 | March 1965 | 15 March 1965 | £4,750,000 | |
| F38 | Arethusa | (a) JS White & Co Ltd, Cowes, Isle of Wight (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) Parsons Marine Turbines Co Ltd, Wallsend-on-Tyne (gearing). |
7 September 1962 | 5 November 1963 | November 1965 | 24 November 1965 | £4,850,000 | |
| F28 | Cleopatra | (a) HM Dockyard, Devonport (b) Cammell Laird & Co (Shipbuilders & Engineers) Ltd, Birkenhead (turbines) (b) John Brown & Co Ltd, Clydebank (gearing). |
19 June 1963 | 25 March 1964 | February 1966 | 4 January 1966 | £5,300,000 | |
| Second 6, Y-136 machinery | ||||||||
| F42 | Phoebe | (a) Alexander Stephen & Sons Ltd, Linthouse, Glasgow (b) Alexander Stephen & Sons Ltd, Linthouse, Glasgow (steam turbines) (b) David Brown & Co Ltd, Huddersfield (gearing). |
3 June 1963 | 8 July 1964 | April 1966 | 15 April 1966 | £4,750,000 | |
| F45 | Minerva | (a) Vickers Ltd, Shipbuilding Group, Newcastle (b) Alexander Stephen & Sons Ltd, Linthouse, Glasgow (steam turbines) (b) David Brown & Co Ltd, Huddersfield (gearing). |
26 July 1963 | 19 December 1964 | May 1966 | 14 May 1966 | £4,700,000 | |
| F40 | Sirius | (a) HM Dockyard, Portsmouth (b) JS White & Co Ltd, Cowes, Isle of Wight (turbines) (b) David Brown & Co Ltd, Huddersfield (gearing). |
9 August 1963 | 22 September 1964 | June 1966 | 15 June 1966 | £5,600,000 | |
| F52 | Juno | (a) JI Thornycroft Ltd, Southampton (b) JI Thornycroft Ltd, Southampton (steam turbines) (b) David Brown & Co Ltd, Huddersfield (gearing) |
16 July 1964 | 24 November 1965 | July 1967 | 18 July 1967 | £5,020,000 | |
| F56 | Argonaut | (a) Hawthorn Leslie, Hebburn (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) David Brown & Co Ltd, Huddersfield (gearing). |
27 November 1964 | 8 February 1966 | September 1967 | 17 August 1967 | £5,000,000 | |
| F47 | Danae | (a) HM Dockyard, Devonport (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) Fairfields (Glasgow) Ltd (gearing). |
16 December 1964 | 31 October 1965 | October 1967 | 7 September 1967 | £5,720,000 | |
| Broad-beamed Leander Y-160 machinery | ||||||||
| F75 | Charybdis | (a) Harland & Wolff Ltd, Belfast (b) Vickers Ltd, Engineering Group, Barrow-in-Furness. |
27 January 1967 | 28 February 1968 | June 1969 | 2 June 1969 | £6,330,000 | |
| F58 | Hermione | (a) Yarrow & Co Ltd, Glasgow (b) Alex Stephen & Sons Ltd, Linthouse, Glasgow (steam turbines) (b) Vickers Ltd, Engineering Group, Barrow-in-Furness (gearing). |
6 December 1965 | 26 April 1967 | July 1969 | 11 July 1969 | £6,400,000 | |
| F60 | Jupiter | (a) Yarrow & Co Ltd, Glasgow (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) Vickers Ltd, Engineering Group, Barrow-in-Furness (gearing). |
3 October 1966 | 4 September 1967 | August 1969 | 9 August 1969 | £6,100,000 | |
| F69 | Bacchante | (a) Vickers Ltd, Shipbuilding Group, Newcastle (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) Vickers Ltd, Engineering Group, Barrow-in-Furness (gearing). |
27 October 1966 | 29 February 1968 | October 1969 | 17 October 1969 | £6,200,000 | |
| F57 | Andromeda | (a) HM Dockyard, Portsmouth (b) JS White & Co Ltd, Cowes, Isle of Wight (steam turbines) (b) David Brown & Co Ltd, Huddersfield (gearing). |
25 May 1966 | 24 May 1967 | December 1969 | 2 December 1968 | £6,700,000 | |
| F71 | Scylla | (a) HM Dockyard, Devonport (b) JS White & Co Ltd (turbines) (b) David Brown & Co Ltd (gearing). |
17 May 1967 | 8 August 1968 | February 1970 | 12 February 1970 | £6,600,000 | |
| F12 | Achilles | (a) Yarrow & Co Ltd, Glasgow (b) JS White & Co Ltd (turbines) (b) David Brown & Co Ltd (gearing). |
1 December 1967 | 21 November 1968 | July 1970 | 9 July 1970 | £6,270,000 | |
| F16 | Diomede | (a) Yarrow & Co Ltd, Glasgow (b) JS White & Co Ltd (turbines) (b) David Brown & Co Ltd (gearing). |
30 January 1968 | 15 April 1969 | April 1971 | 2 April 1971 | £5,980,000 | |
| F70 | Apollo | (a) Yarrow & Co Ltd, Glasgow (b) JS White & Co Ltd (turbines) (b) David Brown & Co Ltd (gearing). |
1 May 1969 | 15 October 1970 | 10 June 1972 | 28 May 1972 | £6,573,000 | |
| F72 | Ariadne | (a) Yarrow & Co Ltd, Glasgow (b) JS White & Co Ltd (turbines) (b) David Brown & Co Ltd (gearing). |
1 November 1969 | 10 September 1971 | 10 February 1973 | 10 February 1973 | £6,576,000 | |
Read more about this topic: Leander Class Frigate
Famous quotes containing the words construction and/or programme:
“Striving toward a goal puts a more pleasing construction on our advance toward death.”
—Mason Cooley (b. 1927)
“In the case of all other sciences, arts, skills, and crafts, everyone is convinced that a complex and laborious programme of learning and practice is necessary for competence. Yet when it comes to philosophy, there seems to be a currently prevailing prejudice to the effect that, although not everyone who has eyes and fingers, and is given leather and last, is at once in a position to make shoes, everyone nevertheless immediately understands how to philosophize.”
—Georg Wilhelm Friedrich Hegel (17701831)