Cape Cod Canal Railroad Bridge - Design and Construction

Design and Construction

The bridge was constructed beginning in 1933 by the Public Works Administration from a design by firms Parsons, Klapp, Brinckerhoff, and Douglas as well as Mead and White (both of New York), for the United States Army Corps of Engineers, which operates both the bridge and the canal. The bridge has a 544-foot (166 m) main span, with a 135-foot (41 m) clearance when raised, uses 1,100-short-ton (1,000 t) counterweights on each end, and opened on December 29, 1935.

At the time of its completion, it was the longest lift span in the world. It is now the second longest lift bridge in the United States, the longest being the Arthur Kill Vertical Lift Bridge between New Jersey and Staten Island, New York. The bridge replaced a 1910 bascule bridge.

Read more about this topic:  Cape Cod Canal Railroad Bridge

Famous quotes containing the words design and/or construction:

    If I knew for a certainty that a man was coming to my house with the conscious design of doing me good, I should run for my life ... for fear that I should get some of his good done to me,—some of its virus mingled with my blood.
    Henry David Thoreau (1817–1862)

    No construction stiff working overtime takes more stress and straining than we did just to stay high.
    Gus Van Sant, U.S. screenwriter and director, and Dan Yost. Bob Hughes (Matt Dillon)