Its new electric propulsion meant it was rated at 2500hp, giving a maximum speed of 90mph and weighing 109 tons. In addition, it was also converted from Co-Co to A1A-A1A wheel arrangement when the centre traction motor from each bogie was removed. The new traction motor rating (with four motors) was about the same as the original rating (with six motors). This suggests that new traction motors were fitted.

The conversion of the locomotive began in January 1958 when the locomotive was moved from storage at Dukinfield Works to the Bowesfield Works at Stockton-on-Tees. The work involved the removal of the gas turbine unit, main generator, fuel tank, air filters, the centre traction motor from each bogie and all of the ancillary equipment used for the gas turbine unit.

Once the locomotive had been stripped, the new electrical equipment was installed which included the transformer, the Stone-Faiveley Pantograph (for which a section of the roof had to be lowered), a Brown Boveri air blast circuit breaker and the Hackbridge-Hewittic mercury arc rectifier units.

The cabs of the locomotive were converted from Western Region right-hand drive to the standard British Rail left-hand drive arrangement. The rebuilt locomotive was completed and ready for trials in October 1958. It retained its original BR black livery, with a silver stripe around the middle of the body and silver numbers.

Read more about this topic:  British Rail Class 80

Famous quotes containing the word conversion:

    The conversion of a savage to Christianity is the conversion of Christianity to savagery.
    George Bernard Shaw (1856–1950)