Important Dates
- 1994 – September, EPA/DEQ issue Record of Decision (ROD) for Butte Mine Flooding Operable Unit.
- 1996 – April, Montana Resources (MR) and ARCO divert Horseshoe Bend (HSB) drainage water away from Berkeley Pit to slow filling rate, per ROD.
- 2000 – July, MR suspends mining operations due to high energy costs; HSB water allowed to flow back into pit, increasing pit filling rate.
- 2002 – March, USEPA and Montana Department of Environmental Quality (MDEQ) enter into a Consent Decree with BP/ARCO and the Montana Resources Group (known as the Settling Defendants) for settlement of past and future costs for this site.
- 2002 – Fall, USEPA and MDEQ issue order for Settling Defendants to begin design of water treatment plant for HSB water. Settling Defendants issue contract and begin construction of treatment plant.
- 2003 – November, MR resumes mining operations.
- 2003 – November 17, HSB water treatment plant comes on line slowing pit filling rate.
Read more about this topic: Berkeley Pit
Famous quotes containing the words important and/or dates:
“What we believe is more important than our material existence, therefore warfare is a legitimate extension of values.”
—Edward Johnson (b. 1915)
“Dates are stupidly annoyingwhat we want is not dates but taste;Myet we are uncomfortable without them.”
—Henry Brooks Adams (18381918)
Related Phrases
Related Words