Advanced CANDU Reactor - Operational Cost

Operational Cost

The ACR has a planned lifetime capacity factor of greater than 93%. This is achieved by a three year planned outage frequency, with a 21-day planned outage duration and 1.5% per year forced outage. Quadrant separation allows flexibility for on-line maintenance and outage management. A high degree of safety system testing automation also reduces cost.