The tunnel was constructed between 1996 and 2000 by Transfield–Obayashi Corporation Joint Venture. Prior to its opening to traffic, the tunnel was opened to the public to walk through from Southbank to Burnley, on 16 December 2000.

The tunnel was opened to traffic on 22 December 2000. In February 2001 it was found that a wall panel was cracked with 5 litres of water a second entering the tunnel. The cause was later found to be floor sections lifting from water pressure, and modifications to correct this being approved in November 2001. Also in 2001 Transfield Obayashi Joint Venture agreed to pay Transurban $157 million in damages in an out-of-court settlement over late completion of the tunnel.

Transurban launched further legal action against the Transfield Obayashi Joint Venture in 2007, after radar tests indicated the tunnel walls were thinner than that specified in the contract, possibly resulting in the tunnel not lasting for the proposed 100-year design life. Further tunnel leaks were also discovered in 2007, but were unrelated to the tunnel fire.

Read more about this topic:  Burnley Tunnel

Famous quotes containing the word history:

    We aspire to be something more than stupid and timid chattels, pretending to read history and our Bibles, but desecrating every house and every day we breathe in.
    Henry David Thoreau (1817–1862)

    In all history no class has been enfranchised without some selfish motive underlying. If to-day we could prove to Republicans or Democrats that every woman would vote for their party, we should be enfranchised.
    Carrie Chapman Catt (1859–1947)

    A great proportion of the inhabitants of the Cape are always thus abroad about their teaming on some ocean highway or other, and the history of one of their ordinary trips would cast the Argonautic expedition into the shade.
    Henry David Thoreau (1817–1862)