External Tank 138 (ET-138) was produced at the Michoud Assembly Facility (MAF) in New Orleans and arrived at the Kennedy Space Center on the Pegasus barge. After offloading, the tank was transported into a checkout cell inside the VAB on 14 July 2010.

NASA initially planned for STS-134 (Endeavour) to fly with the newer ET-138 and for the LON STS-335 (Atlantis) mission to utilize the refurbished ET-122 only in the event that a rescue of Endeavour's crew were required. During Hurricane Katrina, ET-122 was damaged at the Michoud Assembly Facility (MAF) in New Orleans and while the tank was certified as completely flight-worthy after its repairs were completed, NASA management ruled that ET-122 posed a slightly higher risk of losing foam from the repaired areas and therefore assigned it to the STS-335 mission that would likely never fly. However, once it was decided to fly Atlantis on a full STS-135 mission, the tank assignments were swapped so that in the event STS-134 (Endeavour) were to suffer damage from ET-122, Atlantis with the newer and less risky ET-138 would be poised to rescue Endeavour's crew.

In early December 2010, ground technicians installed the main engines on Atlantis. The Shuttle received the center engine on 7 December 2010, followed by the lower-right engine and the lower-left on 8 and 9 December 2010 respectively inside Orbiter Processing Facility (OPF-1). The event marked the last set of main engines ever to be installed on a space shuttle.

Stacking operations of the Solid Rocket Boosters (SRBs) for the mission commenced in the evening hours of 29 March 2011. Technicians inside the VAB, lifted the left-aft segment from the handling crate and carefully maneuvered into High Bay No. 1 and finally onto the mobile launch platform. The booster stacking was completed in mid April. The completed boosters had a mixture of refurbished and unflown elements (11 sections on each booster). For example, the forward dome for the right-hand booster is new, while the upper cylinder on the left booster flew with STS-1 – the historic maiden flight of Space Shuttle Columbia. (For detailed information on the STS-135 boosters, see)

After completing the assembly process, the ET-138 was mated to the SRBs on 25 April.

Read more about this topic:  STS-135

Famous quotes containing the word shuttle:

    And the shuttle never falters, but to draw an encouraging conclusion
    From this would be considerable, too odd. Why not just
    Breathe in with the courage of each day, recognizing yourself as one
    Who must with difficulty get down from high places?
    John Ashbery (b. 1927)