Designed by Sir Maurice Fitzmaurice, the Engineer to the London County Council, the tunnel's construction was authorised by the Thames Tunnel (Rotherhithe and Ratcliff) Act of 1900 despite considerable opposition from local residents, nearly 3,000 of whom were displaced by the tunnel works.

The work took place between 1904 and 1908, executed by the resident engineer Edward H. Tabor and the contractors Price and Reeves at a cost of about £1 million. The tunnel was excavated partly using a tunnelling shield and partly through cut-and-cover methods. The entrance arches of the tunnel are in fact the cutting edges of the original tunnelling shield, which measured 30 feet 8 inches (9.35 m) in diameter, forming in effect a loading gauge for the tunnel.

Read more about this topic:  Rotherhithe Tunnel

Famous quotes containing the word construction:

    There’s no art
    To find the mind’s construction in the face.
    William Shakespeare (1564–1616)

    The construction of life is at present in the power of facts far more than convictions.
    Walter Benjamin (1892–1940)

    There’s no art
    To find the mind’s construction in the face:
    He was a gentleman on whom I built
    An absolute trust.
    William Shakespeare (1564–1616)