CPR-1000

The most numerous reactor type under construction is the CPR-1000, with fifteen units under construction as of June 2010, and another 15 approved and proposed. This reactor type is a Chinese development of the French 900 MWe three cooling loop design imported in the 1990s, with most of the components now built in China. Intellectual property rights are retained by Areva however, which limits CPR-1000 overseas sales potential.

AP1000

The Westinghouse AP1000 is the main basis of China's move to Generation III technology, and involves a major technology transfer agreement. It is a 1250 MWe gross reactor with two coolant loops. The first four AP1000 reactors are being built at Sanmen and Haiyang, for CNNC and CPI respectively. At least eight more at four sites are firmly planned after them.

EPR

In 2007 negotiations were started with the French company Areva concerning the European Pressurized Reactor (EPR), third generation reactors. Two Areva EPR reactors are being built at Taishan, and at least two more are planned (see section below on Embarking upon Generation III plants). Areva says the reactors are 4590 MWt, with net power 1660 MWe.

In October 2008, Areva and CGNPC announced establishment of an engineering joint venture as a technology transfer vehicle for development EPR and other PWR plants in China and later abroad. The JV will be held 55% by CGNPC and other Chinese interests, and 45% by Areva. It will engineer and procure equipment for both the EPR and the CPR-1000.

China plans to develop a domestic program to become self-sufficient in reactor design and construction, as well as other parts of the fuel cycle, though they currently operate using imported Uranium. Shu Guogang, GM of China Guangdong Nuclear Power Project said, "We built 55 percent of Ling Ao Phase 2, 70 percent of Hongyanhe, 80 percent of Ningde and 90 percent of Yangjiang Station."

In 2008, Westinghouse Electric Co., designer of the AP1000, announced that China wants to have 100 nuclear reactors in operation or under construction by 2020.

On 15 July 2010, China’s first CPR-1000 nuclear power plant, Ling Ao-3, was first connected to the grid.

CAP1400 development

In 2008 and 2009 Westinghouse made agreements to work with the State Nuclear Power Technology Corporation (SNPTC) and other institutes to develop a larger version of the AP1000, probably of 1400 MWe capacity, possibly followed by a 1700 MWe design. China will own the intellectual property rights for these larger designs. Exporting the new larger units may be possible with Westinghouse's cooperation.

In December 2009, a Chinese joint venture was set up to build an initial CAP1400 near the HTR-10 Shidaowan site. Construction is expected to start in 2013, operating in 2017.

ACPR-1000 development

In 2010 the China Guangdong Nuclear Power Corporation announced the ACPR-1000 design, a further design evolution of the CPR-1000 to a Generation III level, which would also replace intellectual property right limited components. CGNPC aims to be able to independently market the ACPR-1000 for export by 2013.

VVER-1000

Russia's Atomstroyexport was general contractor and equipment provider for the Tianwan AES-91 power plants using the V-428 version of the well-proven VVER-1000 reactor of 1060 MWe capacity. Russia's Energoatom is responsible for maintenance from 2009. Two further Tianwan units will use the same version of the VVER-1000 reactor.

Read more about this topic:  Nuclear Energy In China

Famous quotes containing the word technology:

    The real accomplishment of modern science and technology consists in taking ordinary men, informing them narrowly and deeply and then, through appropriate organization, arranging to have their knowledge combined with that of other specialized but equally ordinary men. This dispenses with the need for genius. The resulting performance, though less inspiring, is far more predictable.
    John Kenneth Galbraith (b. 1908)