Construction and Commissioning

Construction started on October 24, 1961. From June 2 to December 8, 1962, diversion tunnels were driven through the mountain to divert the river's flow around the construction site. The cofferdam that forced the water to use the diversion tunnels was completed on July 30, 1963, construction of the dam started the day after. By autumn 1965, the dam and powerhouse were sufficiently complete to put the first group of five turbines into service, the others were put in service at the end of construction. Commissioning was completed in 1967.