Jal Mahal - Restoration Works

Restoration Works

In the year 2000, Government of Rajasthan entrused to IL&FS the task of finding a permanent solution to the development requirements of the Man Sagar lake and the palace. In 2001, Government of Rajasthan initiated a project for the 'Ecological Restoration of Man Sagar Lake' and the palace in its midst to its past glory and to enhance the tourism potential of the precincts, through the Jaipur Development Authority (JDA) as the nodal agency. It was also recommended that private developers should also be involved in this effort. In the year 2002, the Ministry of Environment and Forests sanctioned through its National Lake Conservation Programme (NLCP), Rs 24.72 crores (about US$ 5 million) and released Rs 17.3 crores (about US $3.46 million) as grant-in-aid with the proviso that the balance amount shall be raised by JDA. JDA initiated steps for restoration and completed 2 kilometres (1.2 mi) tourist trail and a 1 kilometre (0.62 mi)) long promenade, apart from other works.

In 2004, the Rajasthan Tourism Development Corporation took matters in its hands and decided to try and restore the monument to its original glory. They signed an agreement with Jal Mahal Resorts, granting it a 99-year lease to develop 100 acres along the Mansagar Lake (in the middle of which Jal Mahal stands) and the palace.

Joint sector project

The Lake restoration project of the Man Sagar lake area with an estimated investment of Rs 1.5 billion (considered as one of the largest and unique such projects in India) has evolved a plan that has diverse project components. Consequently, there are many project stakeholders and beneficiaries. The project stake holders are: the Government of Rajasthan and their subordinate organizations such as the Public Works Department (PWD), Rajasthan Urban Development Authority (RUIDP), the Jaipur Development Authority (JDA - the nodal agency for implementation of all aspects of the project), the Department of Tourism, Rajasthan Project Development Fund (RPDF) and the Rajasthan Tourism Development Corporation (RTDC) and an Empowered Committee on Infrastructure Development (ECID); the Central Government organizations associated for planning and financing are the Ministry of Environment and Forests (MOE&F) through its National River Conservation Program (NRCP) and ILFS. The Private Sector Developer (PSD) appointed was M/s KGK Consortium. Under the public–private sector partnership model approved by the EICD, PDCOR had prepared the Detailed Project Report (DPR) for the restoration of Man Sagar lake, Jal Mahal restoration and lake precincts development. The total project area for restoration and development approved by ECID was 432 acres (175 ha) comprising the lake with 300 acres (120 ha) water spread, the lake precincts area of 100 acres (40 ha), which subsumed 15 acres (6.1 ha) of submerged land) for tourism development under joint sector cooperation and 32 acres (13 ha) for lake promenade and tertiary treatment facility and related works.

Unique features of the project

The studies indicated two approaches to tackle the nature of environmental degradation that had occurred in the lake, namely, dealing with natural catchment area and concurrently addressing the serious problem of municipal sewerage emerging from large scale urbanization or human settlement. Keeping this broad planning approach in view, under the lake restoration project, the works undertaken involved were: the re-alignment of city drains, de-silting of the lake, construction of artery road from Amber to Mansagar Dam (about 2.7 kilometres (1.7 mi)), construction of check dam in a 100 metres (330 ft) length with silt removed from the lake, creation of three nesting islands for migratory birds, lake front promenade in1 kilometre (0.62 mi)), afforestation and treatment of forest area portion of lake catchment, plantation to stabilize the slopes of bank formation. Afforestation envisaged plantation of local plant species such as Acacia arabica (Desi babool) and tamarix indica (planting close to the water edge where they can grow well), Terminalia arjuna (Arjun ) poplar, Neem and all species of Ficus, which would provide diversity in vegetation and also better habitat diversity for feeding by birds and wild life.

In addition, to remove eutriphication of the lake water and improve its water quality, in-situ Bioremediation process with 140 diffusers & 5 air compressors to aerate and create inversion of the lake bed and stored water was also envisaged. The city sewage, which supplied 7.0 MLD of untreated sewage was treated with Sewerage Treatment Plant (STP) and then led to the lake to maintain its water level, after due removal of nutrients through tertiary treatment. This process involved diversion of the Brahampuri Nala into the Nagtalai Nala by a lined channel to its south. This was then lead through a treatment plant on site to generate secondary level effluent, which was then discharged into an artificial wetland through a hyacinth channel. For this purpose, a Physico Chemical Treatment Plant was also envisaged and the effluent from this plant was taken through artificially created wetlands in an area of 4 hectares (9.9 acres)) (not only to treat the water but also to serve as natural habitat for birds) and through this process the entire eco-system is being re-generated. Vegetation generated in this process is disposed in a composite pit near the lake.

It is also reported that about 500,000 cubic metres of silt was removed from the lake. This silt was then put to use for strengthening of embankment and building of islands as wintering grounds for migratory birds.

After the above initial restoration works of the lake and its feeder system were mostly completed by the JDA, during 2003, private sector developers were invited to develop identified tourism components on the land adjoining the lake. After following the due process, a joint sector undertaking called the PDCOR was formed between the JDA of the Rajastahn Government and the consortia of private developers with lead provided by M/s. KGK Enterprises. The project for tourism development was entrusted to this joint group. The tourism project entailed development of Convention Centre and Art Gallery, Multiplex and Entertainment Centre, Craft Bazaar, Arts and Craft Village, Resort Hotels, restaurants and food courts, public park and gardens including responsibility for restoration and maintenance of the Jal Mahal.

Read more about this topic:  Jal Mahal

Famous quotes containing the words restoration and/or works:

    The King [Charles II] after the Restoration accused the poet, Edmund Waller, of having made finer verses in praise of Oliver Cromwell than of himself; to which he agreed, saying, that Fiction was the soul of Poetry.
    Philip Dormer Stanhope, 4th Earl Chesterfield (1694–1773)

    Audible prayer can never do the works of spiritual understanding, which regenerates; but silent prayer, watchfulness, and devout obedience enable us to follow Jesus’ example. Long prayers, superstition, and creeds clip the strong pinions of love, and clothe religion in human forms. Whatever materializes worship hinders man’s spiritual growth and keeps him from demonstrating his power over error.
    Mary Baker Eddy (1821–1910)