Hobart Class Destroyer - Construction

Construction

Each ship is assembled from 31 pre-fabricated modules or 'blocks', averaging 200 tonnes (200 long tons; 220 short tons) in weight and 15 by 12 by 9 metres (49 by 39 by 30 ft) in size. The nine blocks making up the forward superstructure of each destroyer, containing the most sensitive or classified equipment, are assembled by ASC's shipyard at Osborne, South Australia, where the final assembly of each destroyer will occur. The other 22 blocks for each ship were subcontracted out. On 9 May 2009, two companies were selected to fabricate the additional blocks: NQEA Australia (building the twelve blocks of each ship's hull) and Forgacs Group (building the ten aft superstructure blocks per ship). However, during June, NQEA advised the AWD Alliance that the shipbuilder was undergoing restructuring and may have difficulty in meeting its contracted obligations. The Department of Defence went into negotiations with NQEA and BAE Systems Australia (which had been shortlisted during the initial subcontractor selection process), and at the end of June, transferred all of NQEA's work to BAE.

In October 2010, the 20-by-17-metre (66 by 56 ft) central keel block manufactured by BAE for Hobart had distorted, making it incompatible with other hull sections. The cause of the fabrication errors is unknown: BAE blamed incorrect drawings from designer Navantia, while the AWD Alliance claimed the other two shipyards have not experienced similar problems, and believe first-of-kind manufacturing errors were made by BAE. The delay in reworking the keel block was predicted to set construction back by at least six months.

In late May 2011, the government announced that the delay in building Hobart had increased to between one and two years, and would attempt to reduce the workload on BAE (which is also responsible for superstructure work on the Canberra class amphibious ships) by redistributing up to 13 of the 24 hull blocks the company was slated to build for the first two ships to the other two shipyards. In addition, the three blocks containing each destroyer's hull-mounted sonar are being assembled by Navantia in Spain and the United Kingdom, with the possibility another two hull blocks could be assigned to the Spanish shipyard. An additional nine-month delay was announced in September 2012; this was intended to create a better transition of labour from the destroyers to following shipbuilding projects (replacements for the Collins class submarines and the Anzac class frigates), and achieve some savings in the federal budget.

Hobart's keel was laid down on 6 September 2012.

Originally, the Hobart class destroyers were planned to be operational between December 2014 and June 2017. However, the ongoing delays have prompted the Australian government to announce revised entry-to-service dates in September 2012: Hobart will commission in March 2016, Brisbane is due in September 2017, and Sydney in March 2019.

Read more about this topic:  Hobart Class Destroyer

Famous quotes containing the word construction:

    There is, I think, no point in the philosophy of progressive education which is sounder than its emphasis upon the importance of the participation of the learner in the formation of the purposes which direct his activities in the learning process, just as there is no defect in traditional education greater than its failure to secure the active cooperation of the pupil in construction of the purposes involved in his studying.
    John Dewey (1859–1952)

    Striving toward a goal puts a more pleasing construction on our advance toward death.
    Mason Cooley (b. 1927)

    There’s no art
    To find the mind’s construction in the face.
    William Shakespeare (1564–1616)