Reactor Data
Reactor unit | Reactor type | Net capacity |
Gross capacity |
Construction started (Planned) |
Electricity Grid |
Commercial Operation |
Shutdown |
---|---|---|---|---|---|---|---|
Bushehr-1 | VVER-1000/446 | 915 MW | 1,000 MW | 1 May 1975; 1995 | 3 September 2011 | 30 August 2012 | – |
Bushehr-2 | VVER-1000/446 | 915 MW | 1,000 MW | 30 July 2012 | – | – | – |
Bushehr-3 | VVER-1000/446 | 915 MW | 1,000 MW | 30 July 2013 | – | – | – |
Bushehr-4 | VVER-1000/446 | 915 MW | 1,000 MW | Cancelled | — |