Contingency Sum
A Contingency sum is an item found within a Bill of quantities (BoQ).
The item refers to unforeseeable cost likely to be incurred during the contract.
There are two types of contingency sum. The first refers to a specific item i.e. 'additional alterations to services when installing said shower unit'; where an item for alterations to existing services is not contained within the BoQ but some work is envisaged.
The second type of sum is where money can be allocated to any item, within the BoQ, in the same way as the above example or used as 'additional work to be undertaken by the contractor, at the request of the contract administrator'.
The first is usually approximated by the client’s PQS and the second by the contractors QS (or commercial manager).
Additional requirements is referred as Bill of materials (BOM).
Read more about this topic: Bill Of Quantities
Famous quotes containing the words contingency and/or sum:
“Life, as the most ancient of all metaphors insists, is a journey; and the travel book, in its deceptive simulation of the journeys fits and starts, rehearses lifes own fragmentation. More even than the novel, it embraces the contingency of things.”
—Jonathan Raban (b. 1942)
“To help, to continually help and share, that is the sum of all knowledge; that is the meaning of art.”
—Eleonora Duse (18591924)