Openings Timeline
- In October 1987, the 17.2 km segment Fetești – Cernavodă was opened for traffic. The segment was closed for traffic again in September 2006 for complete rebuilding and reopened in 2007.
- On 4 June 2004, two segments opened for traffic: Bucharest – Fundulea (26.5 km) and Fundulea – Lehliu (29.2 km).
- In November 2004, the 42 km segment Lehliu – Drajna was opened for traffic.
- In June 2006, the 17.2 km segment Fetești – Cernavodă was re-opened for traffic, after major rehabilitation works.
- Between 1 July and 15 September 2006, the 36.8 km segment Drajna – Fetești temporarily opened for traffic in both ways but only on one carriageway.
- On 1 May 2007, the 36.8 km segment Drajna – Fetești was re-opened for traffic.
- On 29 July 2011, the Murfatlar – Constanța segment (21 km, including a part of A4) was inaugurated (initially, on two of the total four lanes).
- On 30 September 2011, the Murfatlar – Constanța segment was completed and opened on both carriageways.
- On 19 July 2012, the Cernavodă – Medgidia segment (20.5 km) was opened for traffic on a single carriageway, and the Medgidia – Murfatlar segment (16.3 km) was opened on both carriageways.
- On 29 November 2012, the Cernavodă – Medgidia segment (20.5 km) was opened for traffic on both carriageways.
Read more about this topic: A2 Motorway (Romania)
Famous quotes containing the word openings:
“There are a thousand unnoticed openings ... which let a penetrating eye at once into a mans soul; and I maintain ... that a man of sense does not lay down his hat in coming into a room,or take it up in going out of it, but something escapes, which discovers him.”
—Laurence Sterne (17131768)