The winter road is constructed by Nuna Logistics and RTL-Robinson every January and takes about six weeks to complete. The first vehicle along each season is a Swedish-made Hägglund army-type reconnaissance vehicle designed to float if it falls through the ice; it tows an ice-thickness-detecting sonar. This is followed by road building equipment including "specialized low ground pressure equipment". The road, built extra wide to avoid blockages during blizzards and to allow opposing trucks to pass, is kept clear of snow, which acts as insulation, throughout the season as removal allows the ice to freeze faster and thicker. The road is 50 m (160 ft) wide on the ice, but narrower on land portages ranging between 12 and 15 m (39 and 49 ft) wide. Once initially built, the road is checked by drilling holes into the ice. If the ice needs to be thickened, water trucks are called in to add water to that specific area. The road is only operational during February and March, an average of 67 days per year. The ice has been proven by engineers to support light vehicle loads at 70 cm (28 in) and increasing to full highway truck loads as the ice thickens. A thickness of 107 cm (42 in) is required for a super B tanker carrying up to 50,000 l (11,000 imp gal; 13,000 US gal) and may weigh up to 42 t (41 long tons; 46 short tons).

On some lakes, traffic may be re-routed to new lanes to avoid damaged or rough sections of ice, and additional "express lanes" allow returning, empty trucks to travel at higher speeds.

The highest allowable speed for fully loaded trucks on the ice is 25 km/h (16 mph) with some areas reduced to only 10 km/h (6.2 mph). Empty trucks have a maximum speed limit of 60 km/h (37 mph) on the ice. Speed limits are strictly enforced by security personnel with radar used to clock speeds just as national and provincial police forces do.

There are three road camps servicing drivers hauling loads along the road, they are at: Dome Lake Maintenance Camp, Lockhart Lake and Lac de Gras. Dome Lake is for maintenance crew and emergency use for drivers, Lockhart Lake provides drivers with food, shower, and a place to do laundry. Lac de Gras is for road crews, emergency use and for driver facilities for drivers travelling north of Ekati.

Truck drivers are not allowed to travel the winter road alone, therefore, up to four trucks are dispatched from Yellowknife every 20 minutes. Heavy and wide loads are dispatched from Yellowknife between 12:00 am and 6:00 am to avoid daily commuter traffic.

The main product shipped is diesel fuel and other materiel includes "cement, tires, prill (ammonium nitrate) for explosives manufacture, and construction materials."

Read more about this topic:  Tibbitt To Contwoyto Winter Road

Famous quotes containing the words construction and/or operation:

    The construction of life is at present in the power of facts far more than convictions.
    Walter Benjamin (1892–1940)

    Waiting for the race to become official, he began to feel as if he had as much effect on the final outcome of the operation as a single piece of a jumbo jigsaw puzzle has to its predetermined final design. Only the addition of the missing fragments of the puzzle would reveal if the picture was as he guessed it would be.
    Stanley Kubrick (b. 1928)