Super Power Building - Project History

Project History

Plans for the Super Power Building project were unveiled in 1993 by the Los Angeles-based Church of Scientology Religious Trust. The site was formerly occupied by the Gray Moss Inn, a turn-of-the-century building across the street from the Scientology-owned Fort Harrison Hotel. The inn had stood empty since being damaged in a 1989 arson fire and the Church of Scientology acquired the land in 1991 after it had been purchased by local property developer Terence J. McCarthy, the owner of T.J.M. Holding and president of Graymoss, Inc.

The architectural firm HOK was hired to deliver the project. Construction officially began by SKANSKA USA in November 1998 and was slated for completion by late 2003. However, work was reported to have fallen well behind schedule and stopped in 2003. The cost of construction was reported to have more than doubled due to rises in the price of steel and labor, with the Church repeatedly issuing fundraising requests to its members. The revised cost was not disclosed but in 2000 it was reported that the cost had risen from the initial estimate of $24 million to $45 million, and a doubling of this figure would put the total cost at over $90 million. The Church also stated that the building had undergone two major redesigns due to its requirement to "keep pace with the quality of construction at other new facilities". In mid-February 2006, the Church hired Gensler, the world's largest architectural firm, to take over the project.

The erratic progress of the project prompted criticism from local government officials and residents. In 2005, the city's code enforcement board ordered the exterior, including landscaping and sidewalks, to be completed by early summer. Frank Hibbard, the Mayor of Clearwater, noted that "the building had become an eyesore, surrounded by dirt and a chain-link fence." The deadline was not met and daily fines of $250 — totalling over $40,000 by the end of 2006 — were levied against the Church.

A Church spokesman announced in April 2006 that the building would be completed by the end of 2007 but this date has slipped repeatedly. Press reports at the time indicated that the Church was aiming to complete the building by March 2008. In November 2006 the city of Clearwater served the Church with a development order to complete the exterior of the building. but by December 2006 construction had not yet resumed and Church officials indicated that "mid 2008" was now the target date. The prolonged delay has adversely impacted other proposed developments that intended to capitalize on the promised increased economic activity from Scientologists visiting Clearwater. Church officials have offered no public explanation of the delays other than "a recurring need to revise interior design schemes in an effort to get it just right." Work on the building was still at a standstill by March 2009; the daily fines levied by the city then totaled $245,000. Construction work was restarted in July 2009 after the completion of renovation of the nearby Fort Harrison Hotel. Scientology officials stated that the building had cost about $40 million up to that point and that completing the interior was expected to increase the total cost to $50 million. No new completion dates were announced, but "as soon as we get the go-ahead from the city, we'll begin".

In September 2009, Church spokesperson Peter Mansell estimated the Super Power Building would be ready for occupancy by fall of 2010. This date passed without the building opening, though the exterior was completed by 2011. In June 2011, the St. Petersburg Times reported that the building had passed inspection and its Certificate of Occupancy had been obtained. The church sought to seek a reduction in the fine levied by the city at the Code Enforcement Board's July or August meeting. Church spokeswoman Pat Harney said, "We are simply following the standard procedures to close out any remaining permit issues." According to city assistant planning director Gina Clayton, since 2000 the church has paid the city, county and state $2.2 million in permit, plan review, impact and other fees. The church said its redesigns needed time. "We build for eternity," former spokesman Ben Shaw told the Times. "When we do that, we want it perfect." The church said it would host a ribbon-cutting and dedication ceremony there later in 2011. It asked the city to reduce its fine by 90 percent, to reflect its "good faith" effort in bringing the building to code, but the city's resident-led Code Enforcement Board, which has a record of leniency and decimating fines, voted unanimously to keep the fines mostly untouched, saying the church had long ignored the city's rules. The fine was set at $413,500, allowing for a reduction to account for months when the church's plans were paused by city review.

As of late January 2013, the Super Power Building had still not been opened, over 14 years after construction began and nearly a decade after it had been supposed to open.

In January 2012, the Village Voice published a number of leaked schematics of the building, including renderings of the planned facilities.

Read more about this topic:  Super Power Building

Famous quotes containing the words project and/or history:

    The common erotic project of destroying women makes it possible for men to unite into a brotherhood; this project is the only firm and trustworthy groundwork for cooperation among males and all male bonding is based on it.
    Andrea Dworkin (b. 1946)

    What is most interesting and valuable in it, however, is not the materials for the history of Pontiac, or Braddock, or the Northwest, which it furnishes; not the annals of the country, but the natural facts, or perennials, which are ever without date. When out of history the truth shall be extracted, it will have shed its dates like withered leaves.
    Henry David Thoreau (1817–1862)