Sunrise Powerlink - Key Documents

Key Documents

Final Project Modification Report: On May 14, 2010, SDG&E submitted the Final Project Modification Report (PMR) to the CPUC and the BLM. The PMR fine-tunes the approved route and enhances the environmental preservation and protection components of the transmission line. These changes were made in order to minimize impacts to sensitive resources, accommodate landowners where possible and reduce engineering constraints. Highlights of the PMR include:

  • More than 40 poles and structures eliminated
  • Access roads reduced by 74 miles (119 km), or nearly 60 percent, through increased use of helicopters for construction and maintenance
  • Permanent impacts to sensitive vegetation communities reduced by 235 acres (0.95 km2)
  • Impacts to Quino Checkerspot Butterfly habitat reduced by a minimum of 58 percent
  • Temporary impacts to Peninsular Bighorn Sheep habitat decreased by an average of 86 percent and permanent impacts decreased by an average of 74 percent
  • Temporary and permanent impacts to U.S. and state waters reduced by 88 percent

Final Environmental Impact Report/Environmental Impact Statement: The Sunrise Powerlink Final Environmental Impact Report/Environmental Impact Statement was filed on October 13, 2008.

Read more about this topic:  Sunrise Powerlink

Famous quotes containing the words key and/or documents:

    Yes, I know.
    Death sits with his key in my lock.
    Not one day is taken for granted.
    Even nursery rhymes have put me in hock.
    Anne Sexton (1928–1974)

    Our medieval historians who prefer to rely as much as possible on official documents because the chronicles are unreliable, fall thereby into an occasionally dangerous error. The documents tell us little about the difference in tone which separates us from those times; they let us forget the fervent pathos of medieval life.
    Johan Huizinga (1872–1945)