St. Mary's has completed all phases of a complete campus reconstruction, the St. Mary's Campus Reconstruction project. The main academic and administrative center has opened on the site of the former sports field, in March 2009. Construction of the new pool/cafeteria and gym/art/music buildings was completed in August 2010. The Multi-Purpose Room and Parking Lot were completed in March 2011.
| Phase | Dates | Description |
|---|---|---|
| Phase 1 | March 2008–March 2009 | Classrooms/Administration Building & Brothers' Residence |
| Phase 2 | April 2009–August 2010 | Gym/Art/Music Building, Pool/Cafeteria Building, Playfield |
| Phase 3 | September 2010–March 2011 | Multi-Purpose Facility, Parking Lot |