According to the plan a new Sofia airport terminal was built to the east of the old terminal and a second runway was constructed alongside the existing one. The old runway has been turned into a taxiway parallel to the newly constructed runway. Both cross the Iskar river. The new runway was opened in August 2006, while the new terminal opened in December 2006.
Total cost of the project was planned at 200 million euros. Finance was secured in 1997-98 from the European Investment Bank (60 million euro), Kuwait Fund for Arab Economic Development (12.3 million Kuwaiti dinars, approximately 41.5 million euro), and the European Union PHARE Programme (7.6 million euro). In August 2000 an ISPA grant of 50 million euro was allocated and in December the financing memorandum was signed.
The construction works were in two lots: the new terminal with its surrounding infrastructure and the new runway. The first lot was allocated to the German branch of Austrian company Strabag, while the second was won by a consortium of Kuwaiti company Mohamed Abdulmohsin al-Kharafi & Sons and UAE-based Admak General Contracting Company.
Read more about this topic: Sofia Airport
Famous quotes containing the word airport:
“Airplanes are invariably scheduled to depart at such times as 7:54, 9:21 or 11:37. This extreme specificity has the effect on the novice of instilling in him the twin beliefs that he will be arriving at 10:08, 1:43 or 4:22, and that he should get to the airport on time. These beliefs are not only erroneous but actually unhealthy.”
—Fran Lebowitz (b. 1950)