Passage Planning - Planning Stages

Planning Stages

Passage planning consists of four stages: appraisal, planning, execution, and monitoring. These stages are specified in International Maritime Organization Resolution A.893(21), Guidelines For Voyage Planning, which are, in turn, reflected in the local laws of IMO signatory countries. The Guidelines specify fifty elements of passage planning, some of which are only applicable in certain situations.

The Guidelines specify three key items to consider in the practice of voyage planning:

  • having and using a voyage plan is "of essential importance for safety of life at sea, safety and efficiency of navigation and protection of the marine environment,"
  • voyage planning is necessary for all types of vessels on all types of voyages, and
  • the plan's scope should be based on all information available, should be "berth to berth," including when under pilotage, and the plan includes the execution and the monitoring of progress.

Voyage planning starts with the appraisal stage. Before each voyage begins, the navigator should develop a detailed mental model of how the entire voyage will proceed. The appraisal stage consists of gathering and contemplating all information relevant to the voyage. Much of this appraisal is done by consulting nautical charts, nautical publications and performing a number of technical tasks such as weather forecasting, prediction of tides and currents, and checks of local regulations and warnings.

Nautical publications are a valuable guide to local conditions and regulations, but they must be updated and actually read to be of any use. These publications could include Sailing Directions and Coast Pilots or similar texts produced by other authorities.

The next stage of the process is known as the planning stage. Once information is gathered and considered, the navigator can begin the process of actually laying out the voyage. The process involves projecting various future events including landfalls, narrow passages, and course changes expected during the voyage. This mental model becomes the standard by which the navigator measures progress toward the goal of a safe and efficient voyage, and it is manifested in a passage plan.

A good passage plan will include a track line laid out upon the best-scale charts available. This track is judged with respect to at least nine separate criteria given in the Guidelines including under-keel clearance, safe speed, air draft, the use of routing and reporting services (TSS and VTS), and the availability of contingencies in case of emergency.

The navigator will draw and redraw the track line until it is safe, efficient, and in line with all applicable laws and regulations. When the track is finished, it is becoming common practice to also enter it into electronic navigation tools such as an Electronic Chart Display and Information System, a chartplotter, an ARPA system, or a GPS unit.

When working in a team environment, the passage plan should be communicated to the navigation team in a pre-voyage conference in order to ensure that all members of the team share the same mental model of the entire trip.

The third stage of passage planning is the execution stage. The IMO was careful to include execution as part of the process of passage planning. This underscores the fact that the Guidelines list a number of tasks that are to executed during the course of the voyage. It also reiterates the captain's responsibility to treat the plan as a "living document" and to review or change it in case of any special circumstances that should arise.

The fourth and final stage of voyage planning is the monitoring stage. Once the voyage has begun the progress of the vessel along its planned route must be monitored. This requires that the ship's position be determined, using standard methods including dead reckoning, celestial navigation, pilotage, and electronic navigation.

According to the Guidelines, the passage plan should always be available to the officer on watch on the bridge. The Guidelines also specify that deviations from the plan should be clearly recorded and be consistent with other provisions of the Guidelines.

Read more about this topic:  Passage Planning

Famous quotes containing the words planning and/or stages:

    For the people in government, rather than the people who pester it, Washington is an early-rising, hard-working city. It is a popular delusion that the government wastes vast amounts of money through inefficiency and sloth. Enormous effort and elaborate planning are required to waste this much money.
    —P.J. (Patrick Jake)

    America is a country that seems forever to be toddler or teenager, at those two stages of human development characterized by conflict between autonomy and security.
    Anna Quindlen (b. 1952)