New Croton Dam - History

History

The original Croton Dam (Old Croton Dam) was built between 1837 and 1842 to improve New York City's water supply. By 1881, after extensive repairs to the dam, which was 50 feet (15 m) high, Old Croton Reservoir was able to supply about 90 million US gallons (340,000 m3) a day to the city via the Old Croton Aqueduct. To meet escalating water needs, the Aqueduct Commission of the City of New York ordered construction of a new Croton system in 1885. Hydro engineer James B. Francis was brought in as a consultant for the construction.

The proposed dam and reservoir were to cover 20 square miles (51.8 km²) of land occupied by public and private buildings, six cemeteries, and more than 400 farms. Condemnation disputes led to "protests, lawsuits, and confusion" before payment of claims and the awarding of construction contracts. The work force on the new dam included stonemasons and laborers who had worked on the original dam. John B. Goldsborough, superintendent of excavations and hiring for the project, also recruited stonemasons from southern Italy, who re-located to New York.

Work began in 1892 at a site four miles (6.4 km) downstream of the original dam, which was submerged by the new reservoir. New Croton Reservoir was eventually able to supply 200 to 300 million US gallons (760,000 to 1,100,000 m3) a day via a new aqueduct that carried water to Jerome Park Reservoir in the north Bronx, New York City.

Building the dam meant diverting the river from its normal path and pumping the riverbed dry. To accomplish this, workers dug a crescent-shaped canal 1,000 feet (300 m) long and 200 feet (61 m) wide in the hill on the north side of the river, secured the canal with a masonry retaining wall, and built temporary dams to control the water flow. The initial construction lasted eight years, and extensive modifications and repairs went on for another six. Working conditions were often difficult. A silent film, The Croton Dam Strike, released in 1900, depicted labor–management problems related to the dam's construction.

The bridge over the spillway was replaced in 1975 and again in 2005. In that same year, because of the September 11 attacks on New York City, the New York City Department of Environmental Protection proposed permanent closure of the road across the top of the dam. Pedestrians and emergency vehicles were allowed to use New Croton Dam Road, but all other traffic was re-routed. The department made plans to replace temporary vehicle barriers with permanent barriers after completion of a New Croton Dam Rehabilitation Project in 2011.

Read more about this topic:  New Croton Dam

Famous quotes containing the word history:

    The history of reform is always identical; it is the comparison of the idea with the fact. Our modes of living are not agreeable to our imagination. We suspect they are unworthy. We arraign our daily employments.
    Ralph Waldo Emerson (1803–1882)

    I believe that in the history of art and of thought there has always been at every living moment of culture a “will to renewal.” This is not the prerogative of the last decade only. All history is nothing but a succession of “crises”Mof rupture, repudiation and resistance.... When there is no “crisis,” there is stagnation, petrification and death. All thought, all art is aggressive.
    Eugène Ionesco (b. 1912)

    While the Republic has already acquired a history world-wide, America is still unsettled and unexplored. Like the English in New Holland, we live only on the shores of a continent even yet, and hardly know where the rivers come from which float our navy.
    Henry David Thoreau (1817–1862)