The rescue response at the working level of Gibraltar was commended, although there was considerable criticism at a local level in Spain, due to the dispute between Spain and Gibraltar.

Removal of the vessel’s fuel was initiated on 15 August with the arrival of the tug Hua-An, later joined by the tug Fotiy Krylov (one of the largest of the world). It was the first priority of the salvage operation to minimise the environmental impact of the collision, followed by operations to refloat the ship. On 20 August the salvage operation turned to the controlled break-up of the ship in two halves and the first reports of a 'minor' oil-spill were reported. It was reported that 500 tons of fuel remained on board. The tug Fotiy Krylov had attempted to move the ship and divers checked the damage, concluding that the ship's structural integrity was sound enough for the removal of fuel to continue. By 24 August, it looked likely that the ship would be refloated, even if only partially to then tow to a safer location.

The salvage companies involved were Tsavliris (based in Greece) and Svitzer Wijsmuller Salvage (Dutch subcontractors). On 14 September 2007, the Government of Gibraltar announced that all fuel had been removed from the vessel, totalling 780 cubic metres. The operation had been hampered by bad weather and the exposed location of the wreck. It was also reported that the ship would not be salvaged in a single piece due to structural damage and would be instead cut in two parts at one-third of its length from the bow. The stern section would be removed first and towed to a safe area, where it would have its cargo removed and then be taken to dry dock in Gibraltar. On completion, the bow part would have been taken apart where it rested.

The operation was scheduled to start in October 2007 with the removal of the stern in November and the bow as late as March 2008. However, the salvage company experienced technical difficulties in cutting up the vessel. Following heavily prolonged bad weather, the vessel broke into two on 22 December 2007, prompting an emergency meeting by the Government of Gibraltar with maritime authorities.

On 28 December 2007, the vessel's insurers placed the salvage operation in the hands of Titan Maritime, one of the world's largest marine salvage companies.

On 6 August 2008, the stern section was lifted and taken to the ship repair yard.

The salvage operation of the New Flame featured on "Salvage Code Red" on the National Geographic Channel on 16 February 2009.

Read more about this topic:  MV New Flame

Famous quotes containing the words recovery and/or efforts:

    Walking, and leaping, and praising God.
    Bible: New Testament Acts, 3:8.

    Referring to the miraculous recovery of a lame man, through the intervention of Peter.

    The dignity of his office is never impaired by the absence of efforts on his part to maintain it.
    Charles Dickens (1812–1870)