Metering Code of Practice
| Code | Range | Configuration |
|---|---|---|
| COP10 | less than 72 kW | One HH whole current meter installed. Introduced for Feb 2009 |
| COP5 | less than 1MW | One HH meter installed |
| COP3 | 1MW to 10MW | Two meters installed, main and check, both recording the same load. The main meter being used for billing. |
| COP2 | 10MW to 50MW | Two meters installed as in COP3, but higher accuracy class meters. |
| COP1 | > 50MW | Very few sites in the UK at this level, generally power stations and connections with the National Grid. |
Read more about this topic: Meter Point Administration Number
Famous quotes containing the words code and/or practice:
“Acknowledge your will and speak to us all, This alone is what I will to be! Hang your own penal code up above you: we want to be its enforcers!”
—Friedrich Nietzsche (18441900)
“Predatory capitalism created a complex industrial system and an advanced technology; it permitted a considerable extension of democratic practice and fostered certain liberal values, but within limits that are now being pressed and must be overcome. It is not a fit system for the mid- twentieth century.”
—Noam Chomsky (b. 1928)