In 1999 the following elements of the bridge were renovated:
- The existing steel-grated roadway deck on the lift span was replaced with a concrete-and-steel orthotropic deck. A new concrete ("Jersey") barrier now separates opposing traffic flows.
- The elevators and electrical systems in the towers were replaced.
- New variable message signs and traffic control devices were installed on the bridge, approach roadways and toll plaza. A new service building was built at the toll plaza.
Read more about this topic: Marine Parkway-Gil Hodges Memorial Bridge