Manitoba Hydro Place - Cost

Cost

MHP was constructed at a cost of C$278 m, or $400 per square foot. This would place the cost of the building much higher than local building developers would typically target for a city that is not expanding rapidly. The building was also financed internally, with a target construction payback period of more than 60 years rather than the much shorter typical return projection.

During the initial phase of construction, in 2006, engineers discovered a higher water table than anticipated. As the basement had originally been designed to accommodate numerous mechanical systems, the building underwent substantial redesign, including its foundation. A level of the basement was also eliminated during the redesign.

Read more about this topic:  Manitoba Hydro Place

Famous quotes containing the word cost:

    I acknowledge that the balance I have achieved between work and family roles comes at a cost, and every day I must weigh whether I live with that cost happily or guiltily, or whether some other lifestyle entails trade-offs I might accept more readily. It is always my choice: to change what I cannot tolerate, or tolerate what I cannot—or will not—change.
    Melinda M. Marshall (20th century)

    Greeting people doesn’t cost you anything except a roll of your tongue.
    Chinese proverb.

    Keeping accounts, Sir, is of no use when a man is spending his own money, and has nobody to whom he is to account. You won’t eat less beef today, because you have written down what it cost yesterday.
    Samuel Johnson (1709–1784)