Magnox - Decommissioning

Decommissioning

The Nuclear Decommissioning Authority (NDA) is responsible for the decommissioning of the UK Magnox power plants, at an estimated cost of £12.6 billion. There is currently debate about whether a 25 or 100 year decommissioning strategy should be adopted. After 80 years short-lifetime radioactive material in the defueled core would have decayed to the point that human access to the reactor structure would be possible, easing dismantling work. A shorter decommissioning strategy would require a fully robotic core dismantling technique.

In addition the Sellafield site which, amongst other activities, reprocessed spent Magnox fuel in its B205 plant, has an estimated decommissioning cost of £31.5 billion. Magnox fuel was produced at Springfields near Preston; estimated decommissioning cost is £371 million. The total cost of decommissioning Magnox activities is likely to exceed £20 billion, averaging about £2 billion per productive reactor site.

Calder Hall was opened in 1956 as the world’s first commercial nuclear power station, and is a significant part of the UK’s industrial heritage. The NDA is considering whether to preserve Calder Hall Reactor 1 as a museum site.

All the UK's Magnox Reactor Sites (apart from Calder Hall) are operated by Magnox Ltd, a Site Licence Company (SLC) of the NDA. Reactor Sites Management Company (RSMC) holds the contract to manage Magnox Ltd on behalf of the NDA. In 2007, RSMC was acquired by American nuclear fuel cycle service provider EnergySolutions from British Nuclear Fuels.

On 1 October 2008, Magnox Electric Ltd separated into two nuclear licensed companies, Magnox North Ltd and Magnox South Ltd.

Magnox North sites Magnox South sites * Chapelcross * Berkeley * Hunterston A * Bradwell * Oldbury * Dungeness * Trawsfynydd * Hinkley Point A * Wylfa * Sizewell A

In January 2011 Magnox North Ltd and Magnox South Ltd recombined as Magnox Ltd.

Read more about this topic:  Magnox