Hibernia Oil Field - Development

Development

Following several years of aborted startup attempts, during which time the federal government was forced to increase its liability stake in the project by forming the Crown Corporation Canada Hibernia Holding Corporation, the Hibernia megaproject began construction of the production platform and gravity base structure in the early 1990s.

The Hibernia offshore oil field is owned jointly by ExxonMobil Canada (33.125%), Chevron Canada Resources (26.875%), Suncor (20%), Canada Hibernia Holding Corporation (8.5%), Murphy Oil (6.5%) and StatoilHydro Canada Ltd (5%).

As the Hibernia field was located in an inhospitable environment consisting of rogue waves, fog, icebergs and sea ice, hurricanes, and nor'easter winter storms, engineering analyses determined that the most appropriate drilling platform would be in the form of a gravity base structure (GBS).

The Hibernia GBS sits on the ocean floor approximately 80 m (260 ft) depth with its topsides extending approximately 50 m (160 ft) out of the water. The platform acts as a small concrete island with serrated outer edges designed to counter icebergs. The GBS contains production storage tanks and the remainder of the void space is filled with magnetite ballast with the entire structure weighing in at 1,200,000 t (1,300,000 short tons). The GBS was constructed in Bull Arm and the "topsides" production and living quarters was attached to the base while floating in Bull Arm, before the integrated unit (production platform and GBS) was towed out to the actual Hibernia field.

Production commenced on November 17, 1997 and Hibernia has proven to be the most prolific oil well in Canada, with initial production rates in excess of 50,000 bbl (7,900 m3) per day from a single well. A dedicated fleet of shuttle tankers continuously operates between the platform and an onshore transshipment facility at Whiffen Head, adjacent to an oil refinery at Come By Chance.

The development of Hibernia involves a considerable amount of drilling services. As of January 1, 2007, over 50 development wells have been successfully drilled from the platform, including several world record "extended reach drilling" wells.

The platform always has at least one logistics support vessel in attendance, which shuttle supplies and provides on-station emergency support. These support vessels are also tasked during the spring and summer months to tow small and medium-sized ice bergs which might collide with the platform, even though the GBS is engineered to withstand such a hit. The crew consists of 280 people who spend 3 weeks on the platform and three weeks on land, flown to and from the platform by helicopter.

The platform has been used to refuel CH-149 Cormorant search and rescue helicopters on long-range missions in the North Atlantic.

Read more about this topic:  Hibernia Oil Field

Famous quotes containing the word development:

    I do seriously believe that if we can measure among the States the benefits resulting from the preservation of the Union, the rebellious States have the larger share. It destroyed an institution that was their destruction. It opened the way for a commercial life that, if they will only embrace it and face the light, means to them a development that shall rival the best attainments of the greatest of our States.
    Benjamin Harrison (1833–1901)

    The proper aim of education is to promote significant learning. Significant learning entails development. Development means successively asking broader and deeper questions of the relationship between oneself and the world. This is as true for first graders as graduate students, for fledging artists as graying accountants.
    Laurent A. Daloz (20th century)