Fort Loudoun Dam - Background and Construction

Background and Construction

In the mid-1930s, TVA drafted its "unified plan," a series of long-term goals that called for the construction of a series of dams along the Tennessee River to provide a minimum 9-foot (2.7 m) navigation channel along the entire length of the river, control flooding in the Tennessee Valley, and bring electricity to the area. The Fort Loudoun project was initially known as a the Coulter Shoals project, named for a site identified by the U.S. Army Corps of Engineers 6 miles (9.7 km) upstream from the present dam site in the early 1930s. After surveying the area, TVA moved the project to the Belle Canton Islands. TVA proposed the project in 1939 and it was authorized on April 18, 1940. Construction began on July 8, 1940, using much of the construction organization that had been used in previous months on TVA's Hiwassee River projects. TVA originally planned to complete the dam in 1944, but the outbreak of World War II brought increased funding and urgency, and the dam was completed and the gates closed August 2, 1943. The first generator went online November 9, 1943 and the second went online January 15, 1944.

The Fort Loudoun Dam project required the purchase of 16,200 acres (6,600 ha) of land and flowage rights. 317 residents, 6 cemeteries, and over 60 miles (97 km) of roads had to be relocated. Construction efforts required 582,000 cubic yards of concrete and 122,000 cubic yards of riprap. Plans originally called for the installation of four 24-megawatt units, but was modified to three 32-megawatt units after the construction of Cherokee Dam alleviated the need for flexibility. The dam's lock was designed by the Army Corps of Engineers and completed in June 1943. The reservoir submerged part of Louisville, Tennessee, and required modifications to Knoxville's riverfront.

In 1942, TVA received approval to build a dam--at the time known as the "Fort Loudoun extension"--across the mouth of the Little Tennessee River, and divert the water via canal into the Fort Loudoun Reservoir. With the new dam extension planned, TVA received authorization for a fourth 32,000-kW generator. However, the War Production Board gave the dam's third and fourth generators a "low priority" rating, which effectively killed funding for the Fort Loudoun extension, and the side project was abandoned. In the 1960s, the Fort Loudoun extension was revived as the Tellico Dam project.

Read more about this topic:  Fort Loudoun Dam

Famous quotes containing the words background and, background and/or construction:

    ... every experience in life enriches one’s background and should teach valuable lessons.
    Mary Barnett Gilson (1877–?)

    In the true sense one’s native land, with its background of tradition, early impressions, reminiscences and other things dear to one, is not enough to make sensitive human beings feel at home.
    Emma Goldman (1869–1940)

    There’s no art
    To find the mind’s construction in the face.
    William Shakespeare (1564–1616)