ESolar - Sierra SunTower

Sierra SunTower

In the summer of 2009, eSolar unveiled the 5 MW Sierra SunTower plant, a commercial facility in Lancaster, California that demonstrates the company's technology. Sierra SunTower is interconnected to the Southern California Edison (SCE) grid and, as of spring 2010, is the only commercial CSP tower facility in North America.

Sierra SunTower includes two eSolar modules. 24,000 heliostats, divided between four sub-fields, track the sun and focus its energy onto two tower-mounted receivers. The focused heat converts feedwater piped to the receivers into superheated steam that drives a reconditioned 1947 GE turbine generator to produce electricity. The steam passes through a steam condenser, reverts back to water through cooling, and the process repeats.

During the 12 months of construction, Sierra SunTower created over 300 temporary jobs. In operation, the site employs 21 permanent employees.

Sierra Suntower has been certified by the California Energy Commission as a renewable energy facility. Power from the facility is sold under a Power Purchase Agreement (PPA) with SCE, providing renewable energy for up to 4,000 homes.

The 5 MW output from Sierra SunTower reduces CO2 emissions by 7,000 tons per year, an amount equivalent to planting 5,265 acres (21.31 km2) of trees, removing 1,368 automobiles from the road, or saving 650,000 gallons of gasoline.

Read more about this topic:  ESolar