ERAM - Implementation

Implementation

The FAA will deploy ERAM at 20 Air Route Traffic Control Centers, the Williams J. Hughes Technical Center, and the FAA Academy.

Step 1: 2006 Replace the current En Route computer backup system with Enhanced Backup Surveillance.

Step 2: 2007 Provide controllers real-time electronic access to weather data, aeronautical data, air traffic control procedures documents, Notices to Airmen, pilot reports, and other information with the En Route Information Display System.

Step 3: 2009 Replace the current En Route Host computer air traffic control with a fully redundant, state of the art system that enables new capabilities and requires no stand-alone backup system.