Cowboys Stadium - Timeline

Timeline

  • 1994: Cowboys owner Jerry Jones says he wants to expand the 65,000-seat Texas Stadium by up to 40,000 seats, add retractable roof panels and install a climate-control system to make the stadium a year-round venue for sporting events, including the Super Bowl, concerts, and conventions.
  • 1997–2000: The Cowboys hold preliminary talks with Arlington officials about building a stadium there. The team also publicly discusses a $260 million plan to upgrade Texas Stadium. In 2000, the Cowboys compile a list of potential stadium sites, which include Grapevine, Coppell, and Arlington. The team continues negotiating with Irving to renovate Texas Stadium.
  • 2001: Jones says Arlington is a leading contender for a $500 million stadium. The primary site considered is the 2,000 acres (810 ha) Lakes of Arlington tract on Farm Road 157. Other cities in the running include Grapevine and Grand Prairie. In October, Jones discusses the new stadium with the mayors of Arlington, Irving, Grapevine, and Dallas.
  • 2003: The Cowboys ask the Irving City Council to extend their lease at Texas Stadium, which expires at the end of the 2008 season, on a year-to-year basis. They narrow their search to sites in Las Colinas and Dallas, and state legislators file bills that would allow Dallas County to increase its hotel occupancy and car rental taxes to pay for a new stadium.
  • 2004: In April, the Cowboys announce plans to build a $650 million stadium at Fair Park in Dallas. The deal requires $425 million in public financing from a 3 percent hotel-occupancy tax and a 6 percent car-rental tax. The deal falls apart in June when Dallas County commissioners say they cannot justify asking voters to approve the team's request for $425 million in public funding. In July, the Cowboys and Arlington announce they are negotiating to locate the stadium near Rangers Ballpark in Arlington (then Ameriquest Field). In August, the Arlington City Council agrees unanimously to put before voters a tax increase that would fund the city's $325 million portion of the project. Voters approve the tax increase on November 2.
  • 2005: Arlington and the Cowboys choose the site south of Randol Mill Road and east of Collins Street for the new stadium. The city begins notifying residents and property owners of its plans to acquire their property. The Cowboys hire the HKS architectural firm to design the stadium. Early blueprints show 414 luxury suites and a two-panel retractable roof. The city completes its sale of $297.9 million in bonds to pay for its portion of the construction. Demolition of houses begins November 1.
  • January 2006: The Cowboys hired Oklahoma-based Manhattan Construction as the general contractor for the stadium and the city completes its land purchases, although it still faces a number of lawsuits over land acquisition. Later that month, Tarrant County work crews begin demolition of more than 150 Arlington residences and small business structures to make room for the stadium.
  • March 2006: Alliance announced between Manhattan Construction and two general contractors, Rayco Construction of Grand Prairie and 3i Construction of Dallas, to manage the stadium's construction.
  • April 2006: Excavation begins by Mario Sinacola and Sons Excavating. By August, they had moved over 1.4 million cubic yards of earth, shaping a 13-to-14-acre (5.3 to 5.7 ha) stadium bowl an average of 54 feet (16 m) deep.
  • August 2006: Two construction cranes are raised on the site.
  • October 2006: The grass amphitheater on Randol Mill Road is leveled to make way for the extension of Baird Farm Road.
  • December 2006: The stadium's structure begins to go up and on December 12, Jerry Jones unveils the in-depth plans and designs of the stadium to the public.
  • January 2007: A construction worker is injured in a 20 ft (6 m) fall.
  • February 2007: Masonry work begins.
  • March 2007: Heldenfels Enterprises awarded the contract to manufacture and erect the pre-cast/pre-stressed concrete structural components and placement of them begins in April.
  • June 2007: Work on the retractable roof, designed by Uni-Systems, starts.
  • July 2007: Exterior facade and enclosure work began.
  • October 2007: First steel arch is completed.
  • February 2008: Second steel arch is completed.
  • June 2008: Jones commissions the world's largest 1080p HDTV, to hang above field.
  • June 2008: An electrician is electrocuted while working on the stadium. Two days before, three people were injured while assembling a crane.
  • 2009: The stadium is scheduled for 'substantial completion' in June. The artificial-turf field was brought into the stadium in July. The Cowboys played their first pre-season home game on August 21 and their first regular-season home game on Sunday, September 20.
  • May 13, 2009: Jerry Jones announced the official name of the new venue as Cowboys Stadium.
  • February 6, 2011: The 2010 NFL Season Super Bowl was hosted at the Cowboys Stadium, which saw the Green Bay Packers defeat the Pittsburgh Steelers in Super Bowl XLV.

Read more about this topic:  Cowboys Stadium