Cambrian Line - Line Upgrade

Line Upgrade

In October 2006, it was announced that Network Rail would pilot the European Rail Traffic Management System on the Cambrian Line. The ERTMS will allow headways between trains using the same track to be reduced without affecting safety, allowing a more frequent service. Should the pilot scheme be successful, the system is expected to be rolled out on other key rural routes within the UK.

The upgrade is expected to cost £59 million and was to be completed by December 2008, but the system was only released, for limited testing between Pwllheli and Harlech, in February 2010. Three signallers from the Machynlleth signalling centre and seven drivers have been trained to operate the new equipment. Ansaldo STS are the principal contractors for the upgrade with Thales as sub-contractors for the Telecomms. Systra is in charge of testing and commissionning the ETCS and interlocking components of the new signalling system.

Ansaldo is installing ERTMS In Cab ETCS (European Train Control System) level 2, class 1, specification V2.3.0. As the name suggests, the driver receives the instructions for movement on the cab display. This level does not require conventional fixed signals - all the existing signals and RETB boards will be removed. Additionally, the line side speed signs will be redundant - drivers are given the appropriate maximum speed on the cab display which shows km/h, not mph.

The Cambrian ERTMS – Pwllheli to Harlech rehearsal commenced on 13 February 2010 and successfully finished on 18 February 2010. The driver familiarisation and practical handling stage of the rehearsal has provided an excellent opportunity to monitor the use of GSM-R voice in operation on this route. The first train departed Pwllheli at 0853hrs in ERTMS Level 2 Operation with GSM-R voice being used as the only means of communication between the driver and the signaller. Network Rail spokeswoman Mavis Choong was unable to give a figure of how much the scheme has cost, but said £400m was being spent installing it across the UK network. She claimed the 14 month delay was caused by the system "being new".

In 2007, a new flat crossing, named "Cae Pawb Crossing", was installed at the intersection of the Cambrian Line and the Welsh Highland Railway.

In October 2010, following completion of testing, the ERTMS system finally entered service between Pwllheli and Harlech and the previous Radio Electronic Token Block system removed. On 18 March 2011, the final commissioning phase for the ERTMS system across the whole Cambrian route commenced including layout alterations at Welshpool and Talerddig which would facilitate a desired increase in service frequency. At 07:20 on the morning of Saturday 26 March 2011, the New ERTMS signalling system was placed into operational use across the Cambrian Line controlled from Machynlleth, some 40 minutes ahead of the planned schedule. Two days of driver familiarisation then followed with passenger operation commencing on the morning of Monday 28 March 2011. An initial assessment by the operating company was not favourable: problems with the design and installation of the in-cab displays were identified and infrastructure failures included the control system becoming "confused" by common train movements, such as changes of speed or shunting into the depot.

Read more about this topic:  Cambrian Line

Famous quotes containing the word line:

    The real dividing line between early childhood and middle childhood is not between the fifth year and the sixth year—it is more nearly when children are about seven or eight, moving on toward nine. Building the barrier at six has no psychological basis. It has come about only from the historic-economic-political fact that the age of six is when we provide schools for all.
    James L. Hymes, Jr. (20th century)