Boston University Bridge - Rehabilitation

Rehabilitation

As of 2008, the bridge deck, including the sidewalks and vehicular surface, were in severe disrepair; the water below was visible through holes in the deck, and the iron stairs leading from Storrow Drive were rusted through. These deficiencies triggered the bridge to be categorized as "structurally deficient" under the federal NBIS standards. Nevertheless, the main structural elements of the bridge have been determined to be sound.

The approximately twenty million dollar rehabilitation project has been among the first undertaken in the Commonwealth's Accelerated Bridge Program by the bridge owner, the Department of Conservation and Recreation.

As of June 2008, one traffic lane and the west-side sidewalk had been closed so that this work could begin. The project was done in 3 phases to keep traffic open throughout construction. The project was projected to wrap up in late November 2011.

On December 21, 2011, the project was substantially complete and the bridge was opened in its final configuration, with one lane entering the bridge in each direction, transitioning on the bridge to two lanes exiting. Two 5-foot bike lines are provided along side the sidewalks.

Read more about this topic:  Boston University Bridge