Important Dates
- 1994 – September, EPA/DEQ issue Record of Decision (ROD) for Butte Mine Flooding Operable Unit.
- 1996 – April, Montana Resources (MR) and ARCO divert Horseshoe Bend (HSB) drainage water away from Berkeley Pit to slow filling rate, per ROD.
- 2000 – July, MR suspends mining operations due to high energy costs; HSB water allowed to flow back into pit, increasing pit filling rate.
- 2002 – March, USEPA and Montana Department of Environmental Quality (MDEQ) enter into a Consent Decree with BP/ARCO and the Montana Resources Group (known as the Settling Defendants) for settlement of past and future costs for this site.
- 2002 – Fall, USEPA and MDEQ issue order for Settling Defendants to begin design of water treatment plant for HSB water. Settling Defendants issue contract and begin construction of treatment plant.
- 2003 – November, MR resumes mining operations.
- 2003 – November 17, HSB water treatment plant comes on line slowing pit filling rate.
Read more about this topic: Berkeley Pit
Famous quotes containing the words important and/or dates:
“As groceries in a pantry gleam and smile
Because they are important weights
Bought with the metal minutes of your pay,
So do these hours stand in solid rows,
The dowry for a use in common life.”
—Karl Shapiro (b. 1913)
“We do NOT know the past in chronological sequence. It may be convenient to lay it out anesthetized on the table with dates pasted on here and there, but what we know we know by ripples and spirals eddying out from us and from our own time.”
—Ezra Pound (18851972)