Agreed Framework - Implementation of The Agreement

Implementation of The Agreement

Soon after the agreement was signed, U.S. Congress control changed to the Republican Party, who did not support the agreement. Some Republican Senators were strongly against the agreement, regarding it as appeasement. Initially U.S. Department of Defense emergency funds not under Congress control were used to fund the transitional oil supplies under the agreement, together with international funding. From 1996 Congress provided funding, though not always sufficient amounts. Consequently some of the agreed transitional oil supplies were delivered late. KEDO's first director, Stephen Bosworth, later commented "The Agreed Framework was a political orphan within two weeks after its signature".

Some analysts believe North Korea agreed to the freeze primarily because of the U.S. agreement to phase out economic sanctions that had been in place since the Korean War. But because of congressional opposition, the U.S. failed to deliver on this part of the agreement.

International funding for the LWR replacement power plants had to be sought. Formal invitations to bid were not issued until 1998, by which time the delays were infuriating North Korea. In May 1998 North Korea warned it would restart nuclear research if the U.S. could not install the LWR. Formal ground breaking on the site was on August 21, 1997, but significant spending on the LWR project did not commence until 2000.

There was increasing disagreement between North Korea and U.S. on the scope and implementation of the treaty. When by 1999 economic sanctions had not been lifted and full diplomatic relations between U.S. and North Korea had not been established, North Korea warned that they would resume nuclear research unless the U.S. kept up its end of the bargain. The U.S. repeatedly stated that further implementation would be stalled as long as suspicions remained that the North Korean nuclear weapons research program continued covertly.

Construction of the first LWR reactor began in August 2002. Construction of both reactors was well behind schedule. The initial plan was for both reactors to be operational by 2003, but the construction had been halted indefinitely in late 2002.

Read more about this topic:  Agreed Framework

Famous quotes containing the word agreement:

    A marriage based on full confidence, based on complete and unqualified frankness on both sides; they are not keeping anything back; there’s no deception underneath it all. If I might so put it, it’s an agreement for the mutual forgiveness of sin.
    Henrik Ibsen (1828–1906)