The van had been placed in the second floor of the car park, and as a result of the blast a 90% of the building was demolished. The reconstruction of the car park started on January 21, while the damage caused inside the terminal, mainly broken windows as well as distorted structures, had already been repaired by the end of January. Works lasted six months and the car park was inaugurated again by then-Minister of Public Works Magdalena Álvarez on September 20, 2007. Many businessmen attended the event, which also paid tribute to the dead. The reconstruction had a total cost of 24.5 million euros, and 15 million more were used to compensate the damage caused to the 2,100 cars parked there at the time of the attack, as well as to repair the terminal building.